By the Unity Power Services team
Unity Power Services replaced 40 aging light poles across Main Street Village, a townhome community in Purcellville, Virginia, over three phases between fall 2025 and August 2026. The project paced the work to the community’s reserve budget, protected buried utilities with hydrovac excavation on the final phase, and finished with a documented pole-by-pole light map for the property manager. The community’s property manager, Arlene Compher, had never seen a more well-organized operation.
Client Introduction
Main Street Village is a townhome community in Purcellville, Virginia, governed by its HOA and managed by American Management of Virginia. We worked alongside Renee Rutherford of American Management of Virginia and Arlene Compher and Bryan Koons of the Main Street Village HOA. Community associations like this one represent the kind of long-term relationship Unity Power Services values most. The work is rarely glamorous, but it is the work that keeps a neighborhood safe after dark.
Property managers answer to homeowners and a board; they work within a capital reserve budget, and they need a contractor who can plan around both. That is the kind of partner we strive to be.
The Challenge
Site lighting is easy to ignore until it fails. At Main Street Village, the original poles were aged and had been damaged over the years by landscaping equipment working close to their bases. A couple of poles by the community pool had already been replaced in prior years, after fixtures lost their glass covers and attracted hornets, an early sign the original poles were past their working life.
Replacing 40 poles across an occupied townhome community brings its own set of problems:
- Buried utilities and tight footprints. Many of the existing poles had originally been installed on top of or close to underground power and water lines, a common issue in older communities where site records have not kept pace with what is actually in the ground.
- Resident disruption. A project like this means asking residents to tolerate crews and equipment in shared spaces for months at a time.
- Budget pacing. A community association funds capital work from its reserves and cannot always absorb a full replacement in a single year. The HOA needed the project budgeted and executed one year at a time.
- Keeping the lights on. Removing and replacing poles across an occupied property means sequencing the work carefully, so residents are never left with dark stretches for long.
The Solution
Unity Power Services approached the project the way we approach every job: with planning ahead of the first shovel and a crew that treats the property as if it were their own.
We phased the work to fit the HOA’s reserve budget. Rather than one disruptive push, the replacement ran in three phases: an initial round in fall 2025, a second in spring 2026, and the final 14 poles in summer 2026, wrapping in August. Pacing the project this way let the HOA budget for it one year at a time instead of funding the entire replacement at once. As well, each phase was a complete piece of work, so the community saw steady progress rather than an open construction site stretching across a year.
We identified utility conflicts before we dug near them. During the first two phases, our crew identified which pole locations sat on top of or near buried power and water lines. That groundwork shaped how the final phase was executed. Rather than digging blind, we brought in Matt Sousa and the Five Star Septic crew to expose those specific pole bases with pressurized water and vacuum excavation, the safest method available for working that close to live utilities. Hydrovac was not used at every base in every phase; it was the right tool for the utility conflicts the earlier phases had already mapped out.
The final day ran on a schedule built around the neighborhood, not just the work. Crews started at 7:30 a.m., timed around the neighborhood’s school bus stop so crews and equipment stayed out of the way of kids waiting for the bus. Matt’s Five Star Septic hydrovac crew worked alongside one Unity Power Services crew to remove the old poles, while a second Unity crew followed close behind, installing and temporarily supporting each new pole as it went in. By around noon, roughly eight poles had been fully replaced, and Jonathan Friend and the Native Roots landscaping crew started restoring the ground behind them. The two crews stayed in step through the afternoon, and by about 3:00 p.m., the hydrovac and pole-installation work was complete, and the landscaping crew had caught up. From there, Native Roots finished with fresh topsoil and grass seed dressing across every disturbed area, so new grass would grow in rather than leaving bare patches.
We walked every pole with the HOA President. In the final phase, Nick from our team and Arlene inspected each pole together, checking condition and confirming pole numbers against the site map. That walk produced the community’s documented light map, which the management team can use for future maintenance and budgeting.
We installed poles built to last. The replacement poles are 12-foot direct-burial fiberglass, paired with new LED fixture heads. Most of the community’s fixtures are LED today. A handful of older heads that were still working were left in place rather than replaced early, and those can be converted to LED a few at a time as the budget allows.
Results at a Glance
- 40 light poles removed and replaced across Main Street Village over three phases, fall 2025 through August 2026
- Hydrovac excavation used on the final phase to protect utility lines identified during earlier phases
- The final day's work coordinated around the neighborhood's school bus schedule for resident and child safety
- Disturbed ground restored with fresh topsoil and grass seed the same day
- Every pole in the final phase inspected and numbered jointly with the property manager
- A current, documented site light map delivered to the management team, including the 12 pool-area lights
Detailed Results
One of our favorite parts of this project is hearing feedback like this. After reviewing the finished work, Arlene sent our team an unprompted message:
“I have NEVER seen a more well organized operation… The planning, organizing the hydro vac team to the landscaping…….was outstanding and we thank you for all the work you put into this to pull it together. We couldn’t have asked for anything better or more pleased with the outcome.”
And:
“I’m sure Bryan Koons will agree with me when I say if everyone we worked with was like Unity Power, our jobs would be sooo much easier.”
That is the standard we hold ourselves to. Planning, safety, and respect for the people who live on the property are not extras we add to a job. They are the job.
The relationship continues. The 12 lights in the pool area were inspected during the same closeout walk. They are in good working condition, and the HOA has decided to hold the pool-area fixture upgrade until spring 2027, pacing that work to the community’s budget the same way the pole replacement was paced. When the community is ready, our team will be too.
Get In Touch
-
417 Browning Court, Suite A
Purcellville, VA 20132
-
Mon-Fri 7:00-5:00
Amazing Feedback About Our Services
William Hurst
"Unity Power did an outstanding job in replacing two of our outdated electric panels in our home. I would recommend them without reservation for completing any electrical work. In my view, they are the best electrical contractor I haver seen. I trust them totally."
Time Leads Me
"Brian and his teams are the best I've ever worked with!! Unity Power takes great care of our neighborhood and I couldn't be more pleased with their service."
Mike Parker
“Outstanding service and very professional. I don't often need electrical work, but the next time I do, I'm calling Brian and the team at Unity Power!”
Stephen Raddie
“Very friendly and professional. They were very quickly able to send someone out, the next day, and were knowledgeable when they arrived”
Louis & Linda
“Great experience all around. From fitting us in the schedule to completion of the work, the Unity team was consistently courteous and professional. Highly recommend.”
Strategic Insights
Site lighting replacement is a good example of work that looks simple on paper and is anything but in the field. The electrical part is the smallest piece. The real work is in the planning: knowing what is buried before the crew digs, sequencing phases so residents are not living beside a construction zone for longer than necessary, timing the most disruptive day around the neighborhood’s own rhythms like a school bus stop, and documenting every pole so the next property manager inherits a map instead of a mystery.
For property managers and community associations across Loudoun County and Northern Virginia, that planning is the difference between a project the board remembers fondly and one they would rather forget. It is also why we are glad to phase a project across budget years when that is what the community needs, rather than pushing a single large project that strains the reserve.
Ways we can help:
- Site, common-area, and pool-area lighting replacement, phased to fit an association's reserve budget
- Hydrovac excavation coordination to protect buried utilities during electrical and site work
- Pole-by-pole documentation and light maps for property management teams
- LED fixture upgrades for existing poles, including pool and common areas, in batches that fit the budget
- OSHA-certified crews backing every phase of the work
FAQ
How long does a multi-phase light pole replacement like this typically take? This project ran across roughly eleven months from the first phase to the last, though active work time was only a few days. The timeline in this case was set by the reserve budget. Main Street Village chose to pace it across budget cycles, so the gaps between phases were a budgeting decision, not a construction one.
Why not just use hydrovac excavation on every pole from the start? Hydrovac is slower and costs more per hole than conventional digging, so it earns its place where buried utilities are a real risk. Using it everywhere would spend reserve money on locations that never needed it.
About Us
Unity Power Services is a locally owned commercial electrical contractor based in Purcellville, Virginia, serving Northern Virginia. Anchored by Master Electricians (VA) and an OSHA-certified crew, the team designs, builds, and maintains electrical systems for developers, general contractors, facility teams, and data centers, and operates on three core values: Respect, Safety, and Professionalism. Learn more about the team.
If you are planning a capital lighting project for your community or portfolio, reach out through our contact page.